On BBA and adoption of SuDS
BBA certification is not a legal requirement, but it is the due-diligence proof many drainage engineers and adopting bodies look for, and they will interrogate why a cheaper product was chosen.
Because a SuDS Approving Body sets the commuted sum from projected maintenance over a 50-year design life, a supplier that hands over ISO/IEC 17025 structural test data, standards conformity and a maintenance plan de-risks the adoption conversation. Unlike a certificate number, that evidence pack can be checked line by line.
Whole-life maintenance
Silt is the real cause of failure for a buried crate in the long term. Certain systems are harder to jet clean if silt enters them than others, so the maintenance design matters as wide-standard Load – a silted, undersized tank quietly stops controlling flooding. Often the best fix is upstream and structural, not a bigger tank.
- Upstream silt trap or catchpit to prevent sediment entering the crate field.
- DN800 inspection access and jetting ports are integrated into the crate field design from the outset.
- Crate capacity sized with an allowance for silt accumulation, in line with CIRIA C737.
- A detailed, written maintenance schedule provided to the adopting authority or asset owner.
Whole-life performance
| Whole-life question |
What the evidence supports |
Provenance |
| Design life used for the commuted sum |
50 years, the basis a SuDS Approving Body works to |
Sector guidance |
| Material degradation in the ground |
Polypropylene does not corrode or spall the way steel and concrete can; the geotextile and geomembrane are the wear items |
Material property |
| Structural margin under a car park |
Vertical compression measured by Intertek under ISO/IEC 17025, reported as a floor at the rig ceiling |
First-party test report |
| Serviceability at year 20 |
Governed by upstream silt control and DN800 access designed in on day one, not by the crate itself |
CIRIA C737 practice |
What isn’t here. We don’t present a whole life cost saving % or payback period as we’ve no UK based, audited project cost data on which to base one. Be wary of any supplier presenting an exact maintenance saving percentage on buried crates – ask them what scheme, what years, who measured it.